|
CAPTIVE
POWER PLANTS
POLICY
ON CAPTIVE POWER GENERATION
Approved
by G.O. of Tamil Nadu in G.O.MS.No.48 Energy dated
22.04.98 and amended subseq - uently in letter no.4020/A1/98-3
dated 22.05.98 and letter No.6551/A1/98-3 dt.25.8.98.
I.
DEFINITIONS :
i)
CONSUMER means any person who is supplied with electric
energy by Tamil Nadu Electricity Board.
ii)
ACTUAL USER OF POWER means one who is not a consumer
but uses power out of captive power generation.
iii)
GRID means electrical network of Tamil Nadu Electricity
Board.
iv)
BILLING MONTH means the period between the date of
meter reading in a particular month and the corresponding
date of meter reading of the immediate succeeding
or preceeding month as the context requires.
v)
AVERAGE POWER FACTOR means the ratio of the kilowatt
hour to the kilovolt amperehour consumed during the
month. The average power factor shall be calculated
to three decimal places and rounded off to two decimal
places.
vi)
OWNER OF CAPTIVE POWER means any person or group of
persons explained under clause 2 below.
vii)
TNEB means Tamil Nadu Electricity Board.
viii)
CPG means Captive Power Generation.
2.
APPLICANT ELIGIBLE FOR INSTALLING CAPTIVE POWER GENERATION
:
Captive
Power Plant can be installed by any of the following
:
(a)
A consumer of electricity
(b)
A group comprising more than one consumer as joint
venture
(c)
An actual user of power but not a consumer
(d)
A group of actual users of power, but not consumer
as joint venture
(e)
A group comprising of both consumers and users of
power as joint venture
3.
STIPULATION ON CAPACITY :
The
captive power plant can be of any capacity. A part
of the power generated by captive power plant shall
be used by the owner himself or by the sister concern(s)
of the owner of the captive power plant.
4.
PERMISSION AND APPROVAL
(i)
Permission for installation of Captive Power Generation
is to be obtained from TNEB under Section 44 of Indian
Electricity (Supply) Act 1948. For captive power generation
of 25 MW and above, TNEB will accord permission under
Section 44 of Indian Electricity (Supply) Act 1948
only after consulting the Central Electricity Authority
as per Section 44 (2A) of Electricity (Supply) Act
1948.
(ii)
Commissioning, approval shall have to be obtained
from Chief Electrical Inspector to Government, if
the capacity exceeds 10 KW. For Generators upto and
inclusive of 10 KW capacity, approval from CEIG is
not necessary.
(iii)
Permission of Government of Tamil Nadu is required
to synchronize and operate with Grid. Owner of CPG
should apply for the above to TNEB and on TNEB’s recommendations,
Government will issue permission.
(iv)
All statutory clearances for setting up the CPG have
to be obtained by the owner of the CPG on his own
accord and TNEB will not be involved in any manner.
4(a)
CONDITIONS FOR USAGE OF CAPTIVE POWER :
Energy
generated from captive power generation :
(i)
can be used by the user of captive power generation
(ii)
can be used by the sister concern of the owner of
captive power generation
(iii)
Balance power after usage in items (I) and (ii) above
will be purchased by TNEB.
(iv)Third
party sale is not permissible.
5.GENERAL
CONDITIONS FOR CAPTIVE POWER GENERATION :
A.
FOR ANY CAPACITY :
(i)
The energy generated from captive power plant has
to be consumed by the owner himself scheme is operative
only when Government declares power cut on consumption
on electricity and quota to individual consumers is
fixed by TNEB.
When
a consumer uses power, out of his captive power generation
and as a result saves part (or full) energy in units
out of the quota fixed to him for a particular month,
he can bank such saved energy with TNEB in his account.
When the energy saved out of the quota is higher than
that generated by captive power, for any particular
month, then banking shall be limited to the units
generated by captive power generator.
The
banking period is one year from 1st October to the
next 30th September. The energy banked during a particular
banking period shall have to be drawn during banking
period or during the succeeding year banking period.
For example, the energy banked from the 1st October,
1997 to the 30th September 1998 shall have to be drawn
during any part of the years from1 st October, 1997
to 30th September, 1999. The balance of energy not
drawn upto 30th September, 1999 out of the energy
banked during the period from1 st October, 1997 to
30th September, 1998 shall automtically gets lapsed
on 30th September, 1999 to TNEB.
6.1
CONDITIONS FOR DRAWAL OF BANKED ENERGY
(i)
For drawal of energy from the banked account, the
demand shall not exceed the sanctioned demand.
(ii)
Banked energy is allowed to be drawn by the sister
concern of the owner of captive power generation on
the condition (i) above.
(iii)
The banking commission to the TNEB will be 2% in terms
of energy.
(iv)
All generators under the scheme will be metered at
generator end at the cost of the owner of the CPG
tested annually and sealed by TNEB.
(v)
Specific approval of the Chairman / TNEB will have
tobe obtained to come under this scheme.
7.
POWER FEED SCHEME :
(i)
The capacity of individual units shall be 2 MVA and
above.
(ii)
If the facitlity detailed in item No.5(A) (ii) is
availed, then such CPG will not eligible to come under
power feed scheme.
(iii)
They shall be operated in parallel with TNEB grid
interfacing at the voltages prescribed below :
Upto
5 MVA capacity :11 KV or 22 KV (according tothe Voltage
System available at that area)
More
than 5 MVA upto 10 MVA : 33 KV or 110 KV (according
to the voltage system available in that area)
More
than 10 MVA capacity 110 KV or 230 KV
(iv)
The power fed into the grid can be wheeled through
TNEB Grid to his own units/sister concerns situated
anywhere in Tamil Nadu.
(OR)
the
power fed into the grid can be sold to TNEB at the
cost fixed by TNEB vide Clause 11.
(v)Wheeling
shall be 15% in terms of energy wheeled in units irrespective
of voltage or distance.
(vi)The
cost of interfacing lines, switchgear, metering and
protection arrangement shall have to be borne by the
owner of captive power generators, but the work will
be executed by TNEB on Deposit contribution Work basis.
(vii)
When the owner of the captive power generator happens
to be a consumer and when the power fed to the TNEB
grid is less than 2 MVA, dedicated line from the location
of the captive power generator to near by TNEB substation
will not be required. The service line itself will
cater to the need to export the power to the TNEB
grid.
(viii)
When the owner of the captive power generator happens
to be a consumer and when the power fed to the TNEB
Grid is more than 2 MVA, then a dedicated feeder to
a nearby substation will be required. If already the
consumer is availing himself of supply through a dedicated
feeder and if the capacity of the feeder is adequate
to carry the quantum of export of power, then the
sance feeder can be used for export of power and no
additional installation is required.
(ix)
In case the dedicated feeder is not adequate to carry
the power exported, then the existing dedicated feeder
has to be strengthened or a new line has to to be
erected.
(x)
For a non-consumer (user) the new interfacing line
of appropriate capacity and voltage shall be at his
cost and will be executed by TNEB.
|